Kestrel Logistics Hub

A distribution centre with a 15-metre clear height and a floor flat enough for high-bay robotics.

Kestrel Logistics Hub

Client

Kestrel Freight

Location

Doncaster

Contract value

£29m

Size

52,000 m²

Programme

11 months

Completed

2023

Case study

Case study

The brief

A distribution centre with a 15-metre clear height and a floor flat enough for high-bay robotics. Kestrel Freight needed a fixed completion date and a contractor willing to hold it.

How we built it

We modelled the full 11 months programme before breaking ground and agreed every long-lead package in the first eight weeks. Structure and envelope ran in overlapping zones so the building was watertight well before fit-out began.

The result

Handed over in 2023 on the agreed date and within the £29m contract sum, with no lost-time incidents on site and a defects list closed inside four weeks.